Fife electrification work that could have taken up to six months done in 18 days, Network Rail says
Engineers worked around the clock during October closures on a £311.5m Scottish Government project to bring battery-electric trains to the Fife railway.

Network Rail says it packed up to six months of work on the Fife railway into 18 days this month, after closing sections of the Fife Circle so that engineers could work around the clock.
The closures ran from 10 to 27 October. The comparison is with weekend closures alone, the company said, and the team also had to work through Storm Boelo.
The job is preparing the line for overhead electric wires, which will power new battery-electric trains. The Scottish Government is investing £311.5m to electrify 118km of railway in Fife and introduce those trains, which are expected to reduce reliance on diesel.
What got done
- Bridges: Structures at Bennochy Road in Kirkcaldy, Muriespot near Coaltown of Balgonie and Main Street in Thornton were demolished and are being rebuilt higher to make room for the wires. Teams installed 29 concrete beams for the new bridges.
- Foundations and masts: More than 200 foundations and 20 steel structures went in, along with four new masts on the Leven line.
- Signalling: 26 pieces of older equipment were replaced around Burntisland, with further upgrades between North Queensferry and Kirkcaldy.
- Lineside: More than 209,000 square metres of vegetation was cleared, and platforms at Cardenden station were modified.



