HS2 tunnels break through into the Old Oak Common station box in west London

Mining teams have dug two 360-metre tunnels through London clay to join London's first HS2 station to the railway beyond it.

A dark tunnel with a train coming out of it
Photo: Anastasia Zolotukhina / Unsplash

Tunnellers working on HS2 have broken through into the giant underground box at Old Oak Common in west London, linking what will be the capital's first station on the high-speed line with the railway beyond it. Rail minister Lord Hendy visited the station after the latest breakthrough.

Each of the two tunnels is 360 metres long. Rather than using the huge boring machines found on most of HS2's other tunnels, crews mined through London clay with tunnel excavators, spraying 30,000m3 of concrete on to the walls as they went. A second, cast concrete lining followed, poured using travelling formwork.

Work started from HS2's Victoria Road crossover box site in May 2024. The route narrows from two tracks to one between the crossover box and the station, which is why the tunnels were mined rather than bored. HS2 Ltd said all 100,000 tonnes of spoil has gone to reuse projects around the UK.

A Jenga-style finish

The northbound tunnel reached the box on 13 October. For both breakthroughs, engineers used a technique HS2 had not tried before: the dividing wall was cut into blocks, which were then pushed out from the station side back into the completed tunnel, a little like pulling pieces from a Jenga tower.

With both tunnels through, there is now an 8.8-mile underground link from Old Oak Common to the West Ruislip portal.

Four lines in one interchange

Old Oak Common will bring together HS2, the Elizabeth line, Great Western Railway and Heathrow Express in one interchange. HS2 Ltd says trains will cover the roughly 140 miles from the station to Birmingham Curzon Street in around 45 minutes, and that the line will more than double peak-time seats between London and Birmingham. Its stated ambition is to deliver the railway from Old Oak Common to Curzon Street by 2037 or earlier, and it expects the station to add £10 billion to the local economy over the next decade.

Tunnelling towards central London carries on. Two boring machines launched from the eastern end of the station box at the start of 2026 are working through a 4.5-mile drive to the future terminus at Euston and are due to arrive in mid-2027.