Oxford station new platform and western entrance targeted for summer 2029
Network Rail has set out the next phase of the station rebuild. Botley Road should stay open, but Roger Dudman Way would close to through traffic while new bridges go in at Sheepwash.

Passengers at Oxford could have a new platform and a second way into the station by summer 2029, under a programme Network Rail published on Thursday. The date depends on funding being released and the main building contract being awarded.
The work is the next stage of the station's expansion, following the replacement of the Botley Road rail bridge. Botley Road reopened to traffic on Sunday 20 September, having been shut at the bridge since April 2023.
What is being built
The plan has three parts: a new through platform, new road and rail bridges at Sheepwash, and a new entrance on the west side of the station. Network Rail says the current design for the western entrance includes ticket machines, ticket gates and toilets. It is also looking at cycle parking and space for dropping off and picking up passengers.
Design work on the entrance has restarted so that it can be sized for newer passenger forecasts. Those take in East West Rail and the Universal resort planned in Bedfordshire. Network Rail expects the revised design to go through planning by mid-2027.
When the work happens
Preparatory work is due in early 2027. The bridges and the new platform come next, and the western entrance is scheduled to be built across 2028 and 2029.
Roads around the station
For drivers and residents, the main change is on Roger Dudman Way. Under the provisional programme it would close to through traffic for around 20 months so the Sheepwash bridges can be built and utility pipes and cables moved. Pedestrian and cycle access would stay, a diversion would be in place for vehicles needing local access, and a road diversion to the north and a temporary footbridge are also planned. Network Rail says it is looking at round-the-clock working on some tasks to shorten the closure, and will publish details of piling and other construction activity once the programme is fixed.
Botley Road and its pedestrian walkways are expected to remain open for the rest of the scheme. Meanwhile, finishing work from the previous stage is going on: the temporary junction from Cripley Road to Roger Dudman Way, permanent railings and paving repairs in Frideswide Square. Work on the new southern walkway along Botley Road is being done overnight.
Trains and timetables
Network Rail says the extra platform would give room for possible future services, including East West Rail and trains between Cowley and London Marylebone, but that no new timetable is being announced as part of this update.
Wider plans
Separate, longer-term ideas for the station include a possible eastern entrance, a cycle hub, better links with other transport and development around Beckett Street. A public consultation on those is provisionally planned for late May to early July 2027. Residents and businesses can contact the project team at OxfordFeedback@networkrail.co.uk.